Lifting equipment pre-use check (LOLER)

LOLER requires lifting equipment to be thoroughly examined by a competent person at set intervals, and PUWER requires it to be inspected and maintained so it stays safe between those examinations. This is the operator's check before use: quick, per item, with the thorough examination date confirmed every time.

4 sections, 15 items

1Identification and examination status

  1. Equipment reference and location confirmed *

    Yes / no
  2. Safe working load (SWL) marked and legible *

    Pass / fail
  3. Report of thorough examination in date *

    Six months for accessories and equipment lifting people, twelve months otherwise, or as the examination scheme sets.

    Pass / fail
  4. Date of the last thorough examination

    Date

2Condition

  1. Hooks: no deformation, cracks, wear or opening of the throat; safety catch works *

    Pass / fail
  2. Chains, wire ropes and slings: no stretched links, broken wires, cuts, kinks, corrosion or burns *

    Pass / fail
  3. Shackles, eyebolts and fittings: correct pins, no distortion

    Pass / fail
  4. Structure and anchor points sound, no cracks or loose fixings *

    Pass / fail

3Function and safety devices

  1. Brakes hold the load with no drift *

    Pass / fail
  2. Limit switches and overload protection operate

    Pass / fail
  3. Controls labelled and return to neutral; emergency stop works *

    Pass / fail
  4. Area clear, ground or floor suitable, lift planned *

    Yes / no

4Sign-off

  1. Defects found (equipment taken out of use if any critical item failed)

    Text
  2. Photo of any defect

    Photo
  3. Operator signature *

    Signature

* Required